漏粪板制作方法

网址:www.loufen.au08.cn  2021-12-27  作者:admin    阅读:

漏粪板制作方法:
Manufacturing method of fecal leakage plate:
1,在漏粪板模具里面涂抹一层废机油(方便脱模,可以有效减少水泥和模具的粘连),放入钢筋网片,主筋在下,副筋在上。
1. Apply a layer of waste engine oil in the mold of fecal leakage plate (convenient for demoulding, which can effectively reduce the adhesion between cement and mold), and put in the reinforcement mesh, with the main reinforcement at the bottom and the auxiliary reinforcement at the top.
2,把模具放在振动平台上面,将搅拌均匀的混凝土(有流动性就行),灌浆到模具里面,边灌入边振动,灌满以后用平头铁锹把表面刮平整。如没有振动平台可以采用土办法振动。
2, put the mold on the vibrating platform, mix the concrete evenly (with fluidity), grout into the mold, and pour into the side vibration. After filling, use the flat shovel to scrape the surface. If there is no vibration platform, the soil method can be used to vibrate.
3,将制作好的漏粪板放置在阴凉平整的地面上,并用篷布盖住,自然晾干24小时即可脱模,冬季可适当延长至48小时。盖土网 防寒布 麻绳 油麻绳 麻刀 沥青麻绳 静压造型线 自动浇注机 铸铁拍门 钢制拍门 玻璃钢拍门
3. Place the prepared fecal leakage board on a cool and flat ground, cover it with tarpaulin, and dry it naturally for 24 hours to demould. It can be appropriately extended to 48 hours in winter.
4,脱模时可以在地上放置一个废旧轮胎,两个人抬着两端往下轻轻一扣即可脱模,脱模之后的漏粪板再浇水保养5-7天。
4. During demoulding, a waste tire can be placed on the ground, and two people can demould by holding both ends down with a slight buckle. The fecal leakage plate after demoulding can be watered and maintained for 5-7 days.